News

Maryland's Highest Court Holds that Design-Bid-Build Contractors Cannot Hold Design Professionals Liable for Defects in Their Work on Large-Scale Public Projects

On February 21, 2017, the Maryland Court of Appeals decided Balfour Beatty Infrastructure, Inc. v. Rummel Klepper & Kahl, LLP, where a general contractor had sought to hold the design firm that developed the plans and specifications for a large public project liable for the economic losses that defects in their designs had allegedly caused the contractor to suffer.  Significantly, the project was design-bid-build and the contractor did not have a contractual relationship directly with the designers.  The question that the case presented was whether the 鈥渆conomic loss doctrine鈥 precluded the contractor from suing them in tort.  Siding with the designers, the court held that the doctrine does apply 鈥渢o large-scale government construction projects such as this one,鈥 and as a result, the contractor could not bring a tort action against the designers for its purely economic losses.

At the heart of the case was a contract between Balfour Beatty Infrastructure and the City of Baltimore for the construction of various upgrades to an existing water treatment plant.  During construction, several significant defects in the plans and specifications for those upgrades came to the fore.  The testing of denitrification cells revealed cracking and leaks directly attributable to their design.  Pipe support systems also proved to be deficient in their design.  Delays in the design work also increased the contractor鈥檚 cost of completing its work. 

Hoping to recover the added cost meeting its obligations, the contractor filed claims against the city and continues to pursue those claims under the city鈥檚 administrative disputes resolution process.  On January 6, 2014, the contractor also brought this action case against the designers. 

At the outset, the Court of Appeals observed that the case law on the economic loss doctrine 鈥渧aries widely.鈥 The court explained that some states 鈥渁pply[] the . . . doctrine to parties in the construction industry to bar tort claims for purely economic losses鈥 while other states focus on the foreseeable fact that design-bid-build contractors will rely on the work that design firms perform and hold that such firms therefore owe such contractors a 鈥渄uty in tort.鈥

In 2000, the Court of Appeals had held that accountants have such a duty to essentially anyone expected and intended to rely on their reports.  Seeking to split the difference between the two lines of authority on the economic loss doctrine, the court expressly rejected a 鈥渃ategorical distinction鈥 between accountants and design professionals but then refused to extend the accountants鈥 鈥渄uty鈥 to the design professionals involved in this particular case.  

The court鈥檚 reasons were two.  The first was that a 鈥渃omplex web of contracts . . . typically undergirds a public construction project.鈥  The second was that the court鈥檚 decision would have implications for 鈥渢he public purse.鈥  The court maintained that the parties to such a construction project 鈥渉ave sufficient opportunity to protect themselves . . . in negotiating [their] contracts.鈥   The court also expressed a fear that 鈥淸i]mposing a tort duty on design professionals will likely correlate with an increase in project costs.鈥

While the case answers some questions, it raises others.  The court was not confronted with evidence that the construction contractor did not, in fact, have an opportunity to negotiate the terms or conditions of its contract with the public owner.  Nor did the court have to deal with evidence that requiring construction contractors to bear undue risk of defects in the plans and specifications for public projects would also have implications for 鈥渢he public purse.鈥   

What is clearer and more encouraging is that the court declined to make a 鈥渃ategorical鈥 decision that design-bid-build contractors cannot, under any circumstances, hold designers liable for economic losses.  In addition, in a footnote, that court expressly acknowledged 鈥渙ther considerations may apply鈥 to private projects.

Last September, 麻豆视频 of America, the Maryland Chapter and the General Building Contractors Association jointly filed a friend-of-the-court brief in the Maryland Court of Appeals in an effort to influence the outcome.  That effort met with some but obviously not complete success.

麻豆视频